Outsource Machining or Buy a Machine: Compare the Same Delivered Work

Build a like-for-like outsourcing versus in-house machining worksheet with a reproducible three-year cost example and explicit capacity assumptions.

BINSING multi-spindle platform for an in-house machining scope review

The short answer

Compare the cost of supplying the same accepted parts over the same period. Separate the outsourced service price, buyer handling, internal variable expenses, annual support and initial investment. Include only costs that differ between the alternatives, identify capacity limits, and keep quality and delivery feasibility visible. A lower drilling cost alone cannot justify replacing an outsourced route that includes additional operations.

Explore equipment for your inquiry

Dual-Servo Multi-Spindle Drilling & Tapping Machine →

Review the published specifications and configuration options against your part drawing before requesting a quote.

Define the delivered unit before entering a price

Write one sentence defining what arrives at your production line: for example, an accepted component with specified drilled and tapped features, cleaned and packed to the agreed requirement. Check which of those tasks the subcontractor performs. Buying a drill-and-tap machine does not automatically bring inspection, deburring, cleaning or packing into the same equipment scope.

Compare the same material ownership and acceptance boundary. If both routes use identical buyer-supplied blanks, that common cost can be shown separately and excluded from the difference. If yield or material purchasing differs, the cost is no longer common. Express each route per accepted part, including the costs of expected rejected or reworked pieces where supported by evidence. Use actual quotations and trial observations for the investment decision.

Fill in the costs once, with a named period

The U.S. Small Business Administration's break-even guidance separates fixed and variable costs. This worksheet uses that distinction for a different question: the cost difference between two supply routes. Its formulas and example are an original purchasing illustration, not supplier pricing or a forecast. Use one currency and distinguish annual amounts from per-part amounts.

Outsource versus in-house comparison worksheet
InputOutsource routeIn-house route
Accepted quantity per yearSame demand QSame demand Q; demonstrate capacity
Variable cost per accepted partService, transport and incremental handlingConsumables, energy, paid production work and incremental handling
Annual incremental fixed expenseRoute-specific contract/support charges, if anyMaintenance/support and other additional annual expenses
Initial investmentAny route-specific initial paymentMachine, fixtures, installation and startup scope
Common costsList separatelyExclude from difference only if truly unchanged
Boundary exclusionsIdentify unpriced activitiesIdentify unpriced activities

Worked example: a three-year, undiscounted cash comparison

Assume 30,000 accepted parts per year for three years. The outsourced route costs USD 1.60 per accepted part, including transport and incremental handling, with no separate fixed or initial expense in this example. The internal route costs USD 0.70 per accepted part plus USD 6,000 per year in additional fixed operating expenses. Its complete initial investment is assumed to be USD 45,000. These are invented round numbers for checking the method, not BINSING prices or achievable production costs.

Outsource total = 3 × 30,000 × 1.60 = USD 144,000. Internal total = 45,000 + 3 × (30,000 × 0.70 + 6,000) = USD 126,000. The internal route is USD 18,000 lower in this simplified three-year comparison. Annual operating cash difference is 30,000 × (1.60 − 0.70) − 6,000 = USD 21,000. With steady annual savings, simple payback is 45,000 ÷ 21,000 = approximately 2.14 years.

The illustration excludes financing, tax, discounting, residual value and changes in working capital. It assumes the internal route can provide the required accepted quantity and that its variable cost remains valid. It is not a discounted investment appraisal. Add any relevant omitted cash flows before approval; do not add depreciation to this cash total after already including the full initial purchase.

Demand sensitivity using the same three-year assumptions
Accepted parts/yearOutsource totalInternal totalInternal cost advantage
20,000USD 96,000USD 105,000−USD 9,000
30,000USD 144,000USD 126,000USD 18,000
40,000USD 192,000USD 147,000USD 45,000

Keep feasibility beside the totals

The high-volume row is meaningful only if the proposed route has demonstrated sufficient capacity with the expected product mix. Also identify the consequence of equipment downtime and the external supplier's actual lead time and minimum order. A hybrid route may keep some work outsourced while bringing one stable operation in-house. Price that specific boundary rather than assuming the entire existing supplier invoice disappears.

Assign one owner to the quote inputs and another to process feasibility. Date each assumption and identify what would change the result: demand, service price, paid labor, yield or support cost. Submit the same accepted-part definition to potential equipment suppliers so the machine quotation can be compared with the service scope.

Prepare your part information

  • One accepted-part definition for both routes
  • Demand, currency and comparison period
  • Per-part, annual and initial costs separated
  • Evidence for internal capacity and variable cost
  • Sensitivity cases and unpriced activities identified
Discuss the production scope →

Common questions

Should we include the same raw material cost twice?

Show it clearly if useful, but an identical common cost does not change the comparison. Include differences caused by material ownership, purchasing terms or actual yield.

Is the lowest three-year total sufficient to buy equipment?

No. Confirm capacity, quality, delivery needs and the complete cash-flow assumptions. The example is a screening worksheet, not an investment recommendation.

Sources and further reading

Request a quote against your current outsourced scope

Send the part drawing, annual demand and operations currently purchased to compare a defined in-house route.

Discuss the production scope ↗